Thursday, May 16, 2013

2013 Street Repairs--Utilities Committee Discussion

At long last, the Engineering Department is putting together its recommendations to report to the Utilities Commitee for the 2013 streets to be resurfaced.  The recommendaiions will be reviewed at the next Committee meeting, scheduled for May 22 at 6:00 p.m. in Council Chambers.  This will open the public discussion that will lead to selection of the streets to be repaired in 2013. 

A copy of the 2013 Street Condition Report prepared by the Engineering Department is at the following link:

2013 Street Condition Report (with estimates)

The meeting is open to the public if you would like to come and lobby for repair of a particular street.

1 comment:

Mark said...

Canterbury Court and Crestview (asphalt portion) are on the final list for approvaly by City Council at the June 3 meeting. West River Rd. N. concrete sealing is also on the list. That rounds out the 4th Ward repairs, other than those we can complete with our own street department.