Work on the Gulf Road bridge over the turnpike is in progress.  Keep this in mind as you travel through that area.  The Engineering Department is making adjustments to the light at Abbe Road/SR 57 to try and relieve congestion at that intersection.

W. River Rd. N. is also underway and the concrete repairs are nearly completed.  The contractor expects to complete the concrete repairs to the center turning lanes by the July 4 holiday and will move to the next phase of the project, from Griswold north to the city line.  W. River Rd. N. traffic will be limited to one-way, northbound ONLY, for the duration of that project.  The project is expected to be completed at the end of October.  Although the contractor is currently ahead of schedule, there are no revisions to the anticipated completion date at this time so that the contractor can account for any unforeseen delays.