Below is information from our Engineering Department regarding the schedule for construction:

Contractor is required to keep all pedestrian routes open between the hours of 7:15 – 9:15 AM and 2:30 - 4:00 PM on school days, and 2) the contractor is required to maintain one lane of traffic in both directions at all times. This schedule is subject to change based on weather or complications due to construction.


9-1 to 9-2 Mobilize and Set Signs

9-6 to 9-9 Remove Manhole Castings and Install Catch Basins

9-12 to 9-16 Pour curbs (at spot locations) and start milling of street

9-19 to 10-15 Mill and Pave balance of project

10-17 to 10-21 Raise Manholes and seal edges